Project | Bateman’s Bay Bridge Upgrade, Sediment Basin Modelling |
Client | John Holland Group |
Project Value | > $100M |
Project Overview | John Holland Group (JHG) engaged JJR to provide temporary (construction phase) sediment basin designs based on modelling scenarios for optimisation of runoff treatment.
These basins formed part of the scope to replace the historic Bateman’s Bay Bridge. |
JJR Involvement | The scope of works for JJR included:
The design was implemented during construction to ensure that clean and dirty water was separated efficiently in compliance with environmental requirements. |