Project Overview |
JJR was engaged by Civil, Mining & Construction Pty Ltd to provide a RPEQ risk assessment and temporary traffic management plan for shuttle flow operations during the construction of various access points at the Clarke Creek Wind Farm. |
JJR Involvement |
JJR’s expert engineers carried out a risk assessment, which was approved by a RPEQ engineer, focusing specifically on the provision of traffic during the construction of Accesses 1 and 2. The team provided the client with a detailed plan for the Shuttle Flow operation during construction of Accesses 1 and 2, which ensured comprehensive planning and compliance with safety standards. |