Project | Pavement and Ramp Design to Realign a Portion of Webb Dock Drive, Port Melbourne |
Client | Port of Melbourne |
Project Value | $1M – $10M |
Project Overview | Webb Dock is a key gateway for importing electrical transformers and other heavy equipment. Port of Melbourne engaged JJR to provide engineering design services to vertically realign a portion of Webb Dock Drive to the proposed finished surface at the western limit of a Port Melbourne tenant site to allow super-massive loads to be transported from ships. |
JJR Involvement | JJR conducted an assessment of proposed works, available historical data, and a vertical geometry check to provide pavement design options. A pre-concept technical memorandum was delivered to the client, prior to preparing detailed design for the pavement and ramp along Webb Dock Drive. The experienced engineers at JJR utilised 12D software, DRAINS and CIRCLY to develop detailed design in accordance with the following standards / guidelines:
|