Project | Blindmouth Creek Crossing – Side Track Design |
Client | Brown Contractors |
Project Value | $1M – $10M |
Project Overview | JJR’s engineering expertise and experience was sought by Brown Contractors to design and certify a temporary side track during the construction of a new two-lane causeway and box culvert at the Blindmouth Creek Crossing. |
JJR Involvement | JJR provided engineering expertise to prepare a temporary side track design as part of the Blindmouth Creek Crossing major road works. The side track design included undertake geometrical and pavement design, wing wall design to act as a retaining wall, and certifying the temporary side track. |