JJR Involvement |
The scope of works for this project included providing structural engineering services for structures 1 to 6 as outlined below:
- Structure 1 – A column that sat on a beam with the beam finishing approximately 1,100mm from the wall. A single cantilever structure column sat 1,500mm inside the wall, meaning it was not supported by the beam;
- Structures 2, 3 and 4 were Position base plates centred over current post-tensioned cable locations, approximately 750mm from the wall;
- Structure 5 – The existing column was located off the beam with the beam being to one side of the centre line of the car park; and
- Structure 6 – The existing column was located off the beam completely with no beam near the structure.
|