Project | Independent Verifier for Fire Main Installation at Appleton Dock (Berths B & C) |
Client | Port of Melbourne Corporation |
Project Value | $1M – $10M |
Project Overview | Port of Melbourne required independent certification and verification of the fire main installation at Berths B & C at Appleton Dock at the Port of Melbourne. |
JJR Involvement | JJR provided independent verification and certification of the fire main at Appleton Dock and ensured the installation was compliant with the design drawings, specification, and standards.
JJR ensured that Witness Points, Hold Points and other quality documentation met the contractual requirements and attended system testing etc. during construction. As independent verifier, JJR ensured that all quality assurance documentation for the fire main system and associated pavement works complied with the contract. |